Trinity Operating Procedures - TOPs
TOP-SUBCO: Control of Parts to Subcontractors
Rev: 5/06/2022
Scope: This procedure covers shipping and control of parts to subcontractors (typically heat treaters, welders, machine shops and platers).
Procedure:
STEP
WHO
WHEN
INFO
TO USE
WHAT
TO DO
THIS SECTION APPLIES
ONLY TO PURCHASE ORDERS GENERATED WITHIN THE FORGING DIVISION
(INCLUDING THOSE GOING TO THE MACHINING DEPARTMENT)
1
Shipping
Clerk, Shipping
Leadman
When
setting job up or upon determining a job needs a subcontract service
Router or
Production Traveler
process
steps;
or if additional step(s) are added, not from the router, then that sub
step must be approved by Engineering and validated by QA.
If
process steps indicate customer requirement for subcontract work,
or if parts are found to need outside rework and subcontractor is not
known notify QA Manager.
2
Engineer*
or QA Manager
If
question
arises as to location of where hardness is to be checked
Specifications
on print or
customer contract
Add
depth
and location of hardness to QC
Print; send one print to Shipping
Clerk
to be attached to heat treat Purchase
Order. Formalize print per TOP-PRINT.
3
Post
Forge Leadman; Shipping
Clerk
Forgings
are to be heat treated
Router
or
Production Traveler
process
steps or notes; print
If the
process plan calls for separation by furnace lot, any reheat treated
parts must be kept separated from the other parts of the same heat code
and coded differently unless all of that heat code is reheat treated in
the same furnace lot.
4
QC
Inspector; Post Forge team member
As
parts
are inspected after forging
Production
Traveler,
container tags, QC Print
Tag
containers with needed post-production steps.
5
Post
Forge Leadman; Post
Forge Specialist; Shipping
Clerk
Time
to
send parts out
Router
or
Production Traveler
process
steps or notes; Production
Traveler;
container tags; Approved
Supplier List
Choose
subcontractor from Approved
Supplier List; prepare preliminary Purchase
Order**;
ensure parts are weighed/counted and containers are properly
tagged/marked; add weight & count to preliminary Purchase
Order;
a
copy of
MTRs (Mill Test Reports)
to accompany parts requiring tensile and
charpy test.
THE REMAINING
STEPS APPLY TO PURCHASE ORDERS GENERATED FROM THE SHIPPING DEPARTMENT.
6
Shipping
Leadman; Shipping
Clerk; Post Forge
Supervisor
After
completing preliminary Purchase
Order
or receiving subcontractor Purchase
Order.
Preliminary Purchase
Order
Complete Purchase
Order
and ensure that arrangements have been made for getting
parts to subcontractor.
7
QA Manager;
Shipping Leadman;
Shipping Clerk
Purchase
Order is
completed except for review and approval
Router
or
Production Traveler
process
steps or notes; Production
and Shipping schedule; Purchase
Order
Review
and
approve each Purchase
Order that is sent to an outside vendor; sign,
stamp or initial, and date.
8
Post
Forge Helper or Driver
After
receiving Purchase
Order and when truck is ready
Container tags; Purchase
Order
Turn
parts
over to subcontractor; have subcontractor sign Purchase
Order, keep 1
copy, give supplier 1 copy; 1 copy placed in P.O. file
9
Authorized
subcontractor
Per
schedule agreed to upon accepting Purchase
Order
Purchase
Order; other needed info such as copy of Process Steps or Customer Specifications
Perform
service ordered (CONTACT APPROPRIATE TRINITY FORGE PERSONNEL TO RESOLVE
ANY QUESTIONS BEFORE PROCESSING PARTS).
10
Shipping
Leadman; Post Forge
Specialist
When
parts
returned
Container tags; Production Traveler;
subcontractor certifications; copy of Purchase
Order
Ensure
all
parts have been returned, all containers have been properly tagged,
remove "Ready for Heat Treat" sticker; move
all parts to next area,
forward Production Traveler
and shipping documents to the QC
Final
Inspector for inspection of parts. NOTE: Machined products
can be
easily damaged in handling -- report any possible damage to Machining Department Supervisor
and QA Manager.
11
QC Production Inspector; QC Manager; QA Manager
Upon
receiving notification of returned parts
Traveler;
print; any
instructions from QC
Supervisor
Examine
parts received to determine if they meet the requirements of
the Purchase
Order; heat codes are traceable, quantities are
correct, and
steps in the Traveler
have not been skipped.
If parts fail inspection: Fill out a "Non-Conformance Form" Inform QC Manager and QA Manager of the rejection. A fomal rejection email will then be send to notify other pertinent parties of the issue.
If parts pass inspection: Pass paperwork (Shipping receiver, BOL and traveler) on to Shipping
Leadman or Shipping
Clerk and
skip Step 12.
12
QC Manager; QA Manager
Upon
notification that parts failed receiving inspection
Inspection
data; copy of Purchase
Order;
print; Production Traveler; Non-Conformance Form
Have
parts
moved to MRB area. Work with the vendor to make the decision to scrap, rework parts internally or return parts to vendor.
Once disposition is made, inform pertinent parties, and insure the "Non-Conformance Form" is properly filled out and approved.
Once
parts have been provcessed in accordance with the "Non-Conformance
Form" and validated to be acceptable per PO requirements, continue
processing of the order.
13
Shipping
Leadman; Shipping
Clerk
Upon
receiving paperwork
Returned
paperwork; copy of Purchase
Order; Production Traveler
Close Purchase
Order and print receiver, send Purchase
Order and receiver to
Accounts Payable Clerk,
send subcontractor certifications to QA
Assistant.
14
Department Leads
At
least
twice per week
Purchase Order status report (M2M)
Check
through outstanding Purchase
Orders to keep up with any that are running
late; involve Scheduling
for any late jobs that are 1) not
easily explained, or 2) beyond 3 days late.
*"Engineer"
refers to the member of the Engineering Department assigned the die in
question. If there is any question as to which Engineer is assigned a
particular die, the VP-Quality
& Engineering decides.
**The
Purchase Order
is computer-generated from M2M
and can only be prepared for a supplier
approved for the particular type of subcontract service.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
2/8/2021 |
Updated steps 11 and 12 to address no conforming product from vendors. |
Dustin Jump |
Todd Shepard |
5/6/2022 |
Updated step 1 to require approval sub step to be added and approved by Engineering and validate by QA |
Dustin Jump |
Todd Shepard |
|
|
|
|
|
|
|
|