Trinity Operating Procedures - TOPs
TOP-QARTI: First Article
Rev: 12/06/2017
Scope: This procedure covers Quality Planning and First Article Inspections of representative parts from the first run of a new product or when there is a significant process change requiring a new First Article Inspection (FAI).
Procedure:
Forging
Engineering Upon receiving
a Customer
Purchase Order for a
new product, the Customer
Service Representative (CSR) e-mails the
VP-Quality &
Engineering a copy of the PO, quoting documents,
specifications, and other items of note. The CSR
creates the first article part number in the M2M Item Master
per TOP-ORDER. The
Forging Engineer
(assigned
to
the customer) begins the FAI process by determining the requirements
for
the FAI. Once determined, the known quality information is forwarded to
the QA Manager. The
QA Manager begins
the process of creating the
Quality Plan.
The Quality Plan
must be approved by the
Forging Engineer. The
Forging Engineer creates the FAI
BOM, Router and Spec ID
from the newly created first article part. These
must be approved by the QA
Manager. Quality
Planning The
Quality Manager
creates a Quality Plan
using the customer purchase order, Customer
Print, and typically
information that comes from the new die hatch meeting. The QA Manager
then
coordinates all quality related activities required to produce parts
that satisfy the customer's requirements. During the review of the
first article, the standard BOM,
Router, and
Customer Specifications
are reviewed. All pertinent and special
information such as inspection instructions, gages, and any inspection
forms needed are added to BOM,
Router, Spec ID system and
sent to the
Forging Engineerfor
review and approval.
Anyone
becoming aware of the need to add
or modify a Quality
Plan is to
notify the QA Manager. First
Article Inspection When a
First Article Inspection is required the Quality Plan
can specify the
CMM Programmer/Operator's
or QC Inspector's
measuring equipment.TOP-MSURE.
The CMM Programmer/Operator
or QC Inspector's
records the results of
the inspection on the inspection record document as assigned by
the Quality Plan. First
Article Inspection Buy off It is the
responsibility of the QA
Manager to arrange for source inspection, when
required, and follow thru till first article is approved and documented
in the company files.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|