Trinity Operating Procedures - TOPs
TOP-MPSMM: MPS Maintenance and Control
Rev: 12/06/2017
Scope: This procedure covers the Machining Department review of product specifications and plans and the creation and update of Machining Procedure Specifications (MPSs) which control all Machining Department work operations, including welding.
Procedure:
STEP
WHO
WHEN
INFO TO USE
WHAT TO DO
1
Machining Department Supervisor,
Machining Superintendent
or Machining Department
Programmer
Upon
receiving
Engineering
Change Notice, drawing revision, specification, Purchase
Order (PO) or other information that might affect the Job Order (JO)
standardized
process
Job Order, print or
advice from Machinists
or others; own observations
Carefully review
the information from a risk perspective and take action to
mitigate any
potential adverse effects or unintended consequences. Review new information
and identify any questions which need to be resolved; work with any
team member, customer or supplier as appropriate to resolve questions
and reach agreement on what is needed in the Standard Router; determine
how well the current Standard Router
meets the needs identified; if any
customer or reference specifications (other than dimensional) are
involved notify QA Manager
per TOP-TPSMM;
ensure that there
is a Standard Router
Operation and Inspection Order
set up for each machining operation,
verify that all Inspection
Orders clearly specify "who", "what", "how",
"when", and "how many" for each operation; verify that all operational
and inspection issues related to handling storage, packaging,
preservation and delivery are covered.
NOTE REGARDING
WELDING OPERATIONS; Welding is a "special" process whereby the results
of the operation cannot be fully determined without destructive
testing. For any welding operation the Standard Router must be
specific concerning
all details of the process (gage settings, amperage, wire, etc.) and of
the welder's qualifications (team position).
2
Machining Department Clerk
Upon
receiving new
information from Machining
Department Supervisor, or feedback from machining department
personnel
Marked
up Traveler with
redlined changes, or new information
Change
Standard Router
in M2M
to reflect new info; print out and forward a copy of the updated
Standard Router
to Machining
Department Supervisor
or Machining Superintendent for review and approval (both
new and updated Standard Routers
get
reviewed).
Note: The MPS spreadsheets are OBSOLETE and should NEVER be updated;
they are for legacy knowledge ONLY.
3
Machining Department Supervisor
or Machining Superintendent
Within
72 hours of
receiving Standard Router
change for review
Standard
Router;
revised drawing,
Customer
Specification or other data deemed needed
Review
Standard Router
versus specs
and other documentation; for welding operations see note in step 1; if
any problems found or potential need seen notify Forging Engineer
or Machining
Department
Programmer,
so note on Standard Router;
if okay, approve Standard
Router
changes and route
to Machining Department Clerk.
4
Machining Department Clerk
Upon
receiving revised Standard Router
Standard
Router
If
problems noted on Standard Router,
return to
step 1 (or, if minor, step 2); if approved,
send Standard Router
to Machining Department
Programmer
if CNC Program
changes are potentially required.
5
Machining Department
Programmer
Upon
receiving revised Standard Router
Traveler; input from Machining Department Leadman, Machining
Department
Programmer, or Forging
Engineer
Change CNC Programs as
necessary per TOP-MORDR
to
reflect Standard Router
change.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|