Trinity Operating Procedures - TOPs
TOP-MFLUX: Magnaflux
Rev: 9/07/2020
Scope: This procedure covers the "special process" of in-house Non-Destructive Testing, sometimes referred to as "Magnaflux Testing".
Procedure:
QC Supervisor will
make
a sample of rework part; tag it as sample part and place in rework bin
for Post Forge Helper
to use as sample for conducting rework. NOTE:
Be extremely careful not to mix rework parts with good parts.
STEP
WHO
WHEN
INFO TO USE
WHAT TO DO
1
QC
Supervisor/QC
Inspector
Upon
verifying and
determining a need for Magnetic Particle Inspection (MPI) testing or
per customer's request
Personal
observation;
Customer
Specifications; Traveler
Verify
Magnetic
Particle Inspection is required, and place a Green Tag
labeled "Ready
for Magnetic Particle Inspection" inside container; take parts to
staging area in Post Forge; notify Post
Forge Supervisor or Post
Forge Leadman of
need for Magnetic Particle Inspection; if Traveler does not
have Magnetic Particle Inspection step have QC Supervisor or Post Forge Supervisor add
step as required.
2
Post
Forge Supervisor or Post
Forge Leadman
Upon
notification
that parts need Magnetic Particle Inspection
Tagged
parts;
Customer
Specifications, Traveler
Add
Magnetic Particle
Inspection steps to Traveler
if required; schedule parts to be
inspected.
3
Magnetic
Particle Inspector (NDT
Level ll)
Upon
notification
that parts need Magnetic Particle Inspection
The
part's identity,
use, material, photo, print or actual part; Customer Specifications
(if
present); earlier Technique
Sheet (if present)
Verify
that there is
a Technique Sheet
available; if there is not a Technique
Sheet for the
job, develop a Technique
Sheet based on latest revision of ASTM E 1444,
Traveler
information or Customer
Specifications; submit Technique Sheet
to Magnetic Particle Inspector (NDT
Level llI); if a Technique
Sheet exists continue with the
inspection process.
4
Magnetic Particle Inspector (NDT
Level llI)
Upon
receiving
Technique
Sheet
Technique
Sheet;
personal knowledge
Review
Technique
Sheet for completion; make any needed corrections, sign
approval;
forward to QA Manager.
5
QA Manager
Upon
receiving
Technique
Sheet
Technique
Sheet
Scan
Technique
Sheet
into system.
6
Magnetic Particle Inspector (NDT
Level ll)
When
inspection of
parts is scheduled
Traveler;
Technique
Sheet; Customer
Specifications (if present); Trinity
Forge Non
Destructive Testing Specification
Conduct
examination
per Technique Sheet
and Trinity ISPEC-MPIWI
looking for
relevant indications (unless specified differently by the customer's
specification or Traveler
none of the following will be acceptable: any
relevant indication 3/16" or longer, no more than 10 relevant
indications in any 6 sq. in. area, four or more relevant indications in
a line separated by 1/16" or less edge to edge, no relevant indications
in pressure contact sealing surfaces); take any questions to Magnetic Particle
Inspector (NDT
Level llI); fill out Magnetic Particle
Inspection Log; if Traveler
requires examination to be certified, work with QA Manager to fill out
NDT Certification
form then sign it and forward to QA
Manager.
7
NDT
Level I or Magnetic
Particle Inspector (NDT
Level ll); QC
Supervisor
When
parts are
inspected and found to need rework
Red
Tag
for rework of
parts; Green MPI
Sticker Tag for parts ready to ship
Mark
parts to show
location of indications that they need rework; place parts in bin
marked with Red
Tag
for rework; place good parts in bin with
ready to ship Green
MPI Sticker;
when all parts are good continue with
Production Floor
Traveler steps.
8
Post
Forge Helper
Upon
receiving parts
from Magnetic Particle Inspection labeled with rework Red Tag
Sample
rework part
labeled by QC Supervisor,
bin with parts marked with rework Red Tag
Rework
parts in
accordance with sample part; place rework parts in new parts bin
labeled with ready for Magnetic Particle Inspection;
continue with process until all indications are completely reworked; if
deemed scrap fill out Scrap
Report and enter in M2M.
9
QA Manager
Upon
receipt of
completed NDT
Certification
NDT
Certification
Verify
that the
certification has been completed per this TOP; e-mail Post Forge Supervisor
that the NDT Certification
has been reviewed and approved;
issue NDT
Certification
to customer per TOP-ORDER
and file NDT Certification
traceability copy on server.
NOTE: The calibration and maintenance procedure for MPI equipment can be found in ISPEC-MPICM. The qualification and certification of NDT personnel can be found in ISPEC-NDTTR .
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
9/07/2020 |
Updated to replace yellow tag with green tag on line 1. |
Dustin Jump |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|