Trinity Operating Procedures - TOPs
TOP-PURCH: Raw Material Purchasing
Rev: 12/06/2017
Scope: This procedure covers the purchasing of raw material (primarily metal bar stock)
Procedure:
STEP
WHO
WHEN
INFO TO USE
WHAT TO DO
1
Buyer
Daily
Customer
order and specifications; inventory info in M2M
Run
and check Material
Outlook spreadsheet; call up On Hand by Location
Report in M2M to
check for having an adequate supply of material that
meets the specifications of the Job
Orders.
2
Buyer
Standard
BOM and Router requires a
change in the
size or a change in the process after the Job Order is opened
M2M
Job Order
number; PDF file of Customer
PO
Update
the Job Order BOM and Router as needed and
email to
Forging Engineer for approval.
3
Forging Engineer
Upon
receipt of an email from Buyer
requesting
approval on the Job Order BOM and Router changes
Job Order BOM and Router; email form Buyer;
customer's original PO
Use
information from Buyer
to review and approve
Job Order BOM and Router changes.
4
Buyer
Upon
identifying the need to purchase material (due to a customer order or a
low stock condition)
Material Outlook
spreadsheet; On Hand by Location Report in M2M: Material Availability
Report in M2M
Determine
ordering needs per purchasing policy; e-mail, telephone or fax selected
raw material
suppliers with list of needs (material may only be purchased from
suppliers approved per TOP-SAPVL, but
unapproved suppliers may also be asked for
consideration); inquiries for all purchased material and services
related to product we sell must clearly describe the material/services
requirement, including all applicable specifications and
supplemental requirements.
5
Buyer
After
receiving quotations back from suppliers
Supplier
quotations; customer orders; specs
Review
supplier quotations; within 3 business days of quotation solicitation,
if need a waiver on specifications or delivery from the customer, ask
Customer Service
Representative to perform step 4; if an unapproved supplier
needs
to be considered, petition QA
Manager to add supplier to Approved Supplier
List
6
Customer Service Representative
As
requested by Buyer
Customer
order; info from Buyer
Contact
customer, inform them of material availability difficulties and
renegotiate specifications, delivery or price; update in computer;
return to Buyer
7
Buyer
Upon
decision to place purchase order
Supplier
quotations, customer orders;specs
Enter Purchase Order*
information into computer (supplier, grade, size, quantity, delivery,
specifications and price); if customer order is being held pending
material order, complete step 1.
8
Buyer
After
printing
Purchase
Order
Email
Purchase Order
to supplier; file Open PO FIle; submit link to the
current Flowdown
Document
with the Purchase
Order
to the supplier at the
time of order
9
Buyer
As
supplier
acknowledgment arrives
Purchase Order and acknowledgment
Compare
acknowledgment with PO in Open
PO FIle;
if discrepancy, contact supplier
and resolver; attach acknowledgment to PO copy in Open PO FIle
10
Buyer
If
PO needs
to be changed or canceled
Customer
change order, notice from supplier, etc.
Negotiate
change with supplier (possibly involving Customer
Service Representative to
negotiate with customer as well); finally change Purchase
Order
in M2M as in
steps 5-7, except "Revised PO" imprinted and sent to vendor
*
Purchasing
Policy:
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|