Trinity Operating Procedures - TOPs
TOP-PREVM: Preventive Maintenance
Rev: 03/10/2021
Scope: This procedure covers preventive maintenance (PM) of equipment.
Procedure:
NOTE:
For maintenance scheduling purposes a "week" is defined as seven days
or eighty hours of machine operation, whichever is longer.
STEP
WHO
WHEN
INFO
TO USE
WHAT
TO DO
1
Warehouse
Administrator or
Maintenance Supervisor
Before
new
equipment installation or major equipment repair / modification
Manufacturer
guidelines, own experience
Generate
AMMS Preventive Maintenance (PM) Work Order for equipment validation
2
Maintenance Manager
After
new
equipment installation or major equipment repair or modification
Part Inspection Sheet, PM Work Order, run chart (if
any)
Confirm
with QC Supervisor that parts conform to specified requirements; if
they do, obtain copies of Part Inspection Sheet and attach to PM Work Order; have Warehouse
Administrator add PM Work Order into history file; if the parts do not
conform, make necessary equipment adjustments to reduce problem
3
Maintenance Manager
As
determines need
Own
ideas,
suggestions from others, manufacturer recommendations
Establish
and modify steps and time cycles for preventive maintenance by adding
or changing master PM Work Orders in AMMS
4
Warehouse
Administrator
Weekly
PM Work Orders produced by AMMS
Send Preventive
Maintenance (PM) Work Order automatically generated by AMMS to the Maintenance Manager
5
Maintenance Manager
Weekly
PM Work Order, own ideas
Schedule
preventive maintenance determined by PM Work Orders generated by AMMS. PM schedule is tracked by the Maintenance Manager for both the forge machine shop.
6
Warehouse
Administrator
Monthly
PM Work Orders produced by AMMS
Send PM Work Order automatically generated by
AMMS
to the Machine Shop maintenance nontechnical to record monthly run time
on the CNC Machines; use monthly run time to predict due date of the
1500hour and
3000hour PM's on the CNC Machines. Run times are to be tracked and recorded on a weekly basis for monitoring.
7
Maintenance
Technician
Monthly PM Work Order indicates CNC hours will max out before next month's time to
check run hours
Hours
remaining in each CNC Machine before 1500hour and 3000hour PM
requirement; scheduled hours for CNC Machines to be run in the next
week before next PM Work Order is issued to check hours run on CNC
Machines
Determine
which CNC PM is to be scheduled; check with Machine Shop Production Scheduler for open dates to schedule the PM on individual CNC
machines; coordinate with Warehouse
Administrator to issue PM Work Order for
individual CNC Machines which will be due 1500PM or 3000PM
before
next month's interval for checking run time hours. If unable to stop
for production, detailed reasoning is to be recorded on the weekly hour
tracking sheet.
8
Maintenance
Technician
As
determine need to delay required PM Work Order
on individual CNC Machine (either specific step or whole Work Order)
Current
production scheduling needs for customer's parts;
Production Supervisor
's input for rescheduling the PM
Submit
approved rescheduling of PM in writing to Warehouse
Administrator; forward rescheduling delays of more than two weeks to Manufacturing Manager
for approval
9
Maintenance
Worker
As
assigned
PM Work Order plus plus any extra instructions from Leadman or
Supervisor
Performed
tasks as assigned; mark work done on PM Work Order; add
any notes regarding other work that is needed or regarding ways to
improve the equipment or its operation; report any ideas for points
that ought to be added to the PM Work Order
(to Maintenance Supervisor
or Maintenance Manager); tell appropriate supervisor when equipment
is ready
10
Maintenance Manager
As PM Work Orde returned
PM Work Order plus own observations or tests
Review
any suggestions for improving Preventive Maintenance (PM) Work Order;
return completed PM Work Order to Warehouse
Administrator. Updated master schedule accordingly to track performed preventive maintenance for both forge and machine.
11
Warehouse
Administrator
Weekly
PM Work Order
Enter
info
into AMMS; close work orders that have been completed; if
directed by Maintenance Manager
update master PM Work Order;
verify that any
delays or cancellations have been done in compliance with this TOP and
notify Manufacturing Manager
of any infractions. File all completed work order from both forge and
machine in the same location. Insure all documents have properly been
scanned for a digital back up.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
03/10/2021 |
Updated to reflect current PM process and org chart |
Dustin Jump |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|