Trinity Operating Procedures - TOPs
TOP-PRDEV: Product Development Process
Rev: 12/06/2017
Scope: The Trinity Forge & Machine "Product Development" Core Process.
Procedure:
"Product Development" consists of the series of activities necessary for working with a customer to develop a concept for a forged and/or machined part into the specifications and tooling necessary prior to for production. These are the activities associated with selling, engineering and tooling for both new products and for engineering changes.
Providing the resources necessary for Product Development is the Resource Management process. Actual processing of a parts order is the Order Fulfillment process. Records maintained from Process Development ultimately feed into the Review and Improvement process.
Below, in general order of occurrence, the Process Development activities are outlined showing the primary Trinity Operating Procedure (TOP) associated with each activity.
1. Quoting. See TOP-QUOTE.
2. Developing specifications, tooling, and quality plans for new products, including project management. See TOP-NEWDI.
3. Handling engineering change orders. See TOP-DCORD.
For the complete list of all TOPs within the Product Development Processes, click here.Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|