Trinity Operating Procedures - TOPs
TOP-DCORD: Die Change Orders
Rev: 04/10/2018
Scope: This procedure covers die changes requested by customers. A die change is the process of making customer requested changes to dies which affect the configuration of the final forgings.
Procedure:
STEP
WHO
WHEN
INFO TO USE
WHAT TO DO
1
Anyone
Upon
receiving customer request for a die change
Customer
request, Customer Prints
or 3D model
Forward
information to Customer
Service Representative
2
Customer Service Representative
Upon
receiving customer request for a die change
Customer
request, Customer Prints
or 3D model
Request
a
quote (see TOP-QUOTE);
place Sales Order(s)
on HOLD; forward to the Estimator
3
Estimator
Upon
receiving quote request
Prints
or 3D
model,
customer info
Enter
Quote in Micro Estimating; forward to
Forging Engineer
4
Forging Engineer
Upon
receiving RFQ
RFQ,
prints or 3D
model,
customer info
Review RFQ or customer info, complete
Quote
Spreadsheet for cost and forward back to Estimator
5
Estimator
Upon
receiving RFQ
with cost
RFQ with Quote Spreadsheet, prints or 3D model, customer info
Review RFQ .
6
Customer Service Representative
Upon
receiving RFQ
RFQ, prints,3D model, customer info
Get
customer approval
(obtain their PO) to proceed with die change; enter Sales Order for
die
change.
7
Customer Service Representative
Customer
PO
received
or customer verbal
Customer
PO,
print,
Quote
Place
PO and quote into the Customer
PO Folder;
send
email to VP-Quality &
Engineering; print per TOP-PRINT;
spec
per TOP-TPSMM
8
VP-Quality & Engineering
Email
received instructing die change
Email and
its contents
Review
and
assign to
Forging Engineer
9
VP-Quality & Engineering,
Forging Engineer
Upon
receiving a request to make a die change
Customer PO; Forging
Engineering File
Decide
if
existing drawing needs to be revised or if a new drawing is needed;
initiate TOP-PRINT;
prepare
or revise any affected Die
Layout, Die
Drawings or Machining
Prints (all per TOP-PRINT);
revise or create model, die, and tooling per TOP-SOLID;
if deemed
appropriate, solicit die sinker quotations and initiate sinking of
dies per TOP-SINKER;
estimate
any
changes to material size and such, and update steel size
change in BOM
and Router;
notify
Engineering Assistant to
enter Job Order
for die and/or tooling change
10
Engineering Assistant
Upon
receiving notification from a
Forging Engineer of the need to create a
Job Order
Info
from
Forging Engineer,
Customer Print,
Customer PO
Create
Tooling Job Order
per
Forging Engineer's
instructions
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
10/01/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
04/10/2018 |
Updated steps 3,4,5 and 6 for current practices. |
Todd Sheppard |
Tim Ellis |
|
|
|
|
|
|
|
|
|
|
|
|