Trinity Operating Procedures - TOPs
TOP-FLSPG: Flight and Nuclear Safety Program
Rev: 12/06/2017
Scope: This procedure establishes the control of manufacturing Primary, Critical, and Flight Safety Parts and to control and prevent FOD (Foreign Object Debris) incidents.
Below, in general order of occurence, the control activities are outlined showing the primary Trinity Operating Procedure (TOP) associated with each activity.
The requirements of the FOD Prevention program are specified in TFI ISPEC-FODPV
Procedure:
1. ORDER FULFILLMENT
The procedure covers the review of the contract with the customer which must be successfully completed before the order is scheduled. See TOP-ORDER. FOD risk must be assessed during contract review. The risk must be assigned a level of criticality.
2. CONTROL OF RAW MATERIALS
Inspection of other incoming materials. See TOP-RECOM. Area supervisor must make FOD assessments and report FOD incidents to the FOD Prevention Program Leader.
3. QUALITY CONTROL DURING PRODUCTION
4. CONTROL OF NONCONFORMANCEQuality Control steps directly associated with machining and in-process inspection. See TOP-MOPQC, TOP-QARTI, and TOP-MOPPP. Quality Control including 100% visual inspection and final inspection using the Acceptance Quality Level of entire lot. See TOP-MOPQC. QC inspectors shall be observantand report FOD incidents to the FOD Prevention Program Leader.
Raw Material Nonconformance. See TOP-RMNON. Product Nonconformance. See TOP-NOCON. Customer returns. See TOP-RTRNS. FOD incidents must be reported to the FOD Prevention Program Leader.
5. PERSONNEL
Each Team Member that processes any Primary, Critical, or Flight Safety Parts or Nuclear Parts has Flight and Nuclear Safety Training and testing. The minimum score is 80%. See TOP-TFTMM, TOP-TRAIN and TFTM-FSAT. Each team member shall be trained to the requirements of the FOD Prevention Program. Each team member shall be aware of the FOD risk assessment level in their area.
6. AUDIT
An annual audit is performed and documented to assure controls exist to process Primary, Critical, or Flight Safety Parts and for Nuclear Parts. See TOP-IAUDT . FOD Prevention and Assessments will be subject to Mini-audits per TOP-IAUDIT.
7. RESOURCE MANAGEMENT - ADMINISTRATIVE MANAGEMENT
All other customer requirements that are specific to that customer's quality requirements and PO are listed in the customer information screen under the User Define tab in Made2Manage (M2M). SeeTOP-TPSMM. Top Management shall be committed to the FOD Prevention Program and the results of the FOD Prevention Program shall be reviewed during Management Review.
Release Date
Description of Change
Owner
Approver
12/06/2017
Updated to comply with revised Quality Manual and new TOPs format.
Tim Ellis
Todd Sheppard
Documents are controlled only when viewed on-line at trinityforge.com in the original English -- printed copies or translations are not controlled documents.