Scope: This procedure covers the use of statistical techniques throughout the company's quality system.

Procedure:

STEP WHO WHEN INFO TO USE WHAT TO DO
1 Any team member Upon having an idea for using SPC  or should a customer Purchase Order require SPC process monitoring Own ideas or research Make suggestion to QA Manager regarding use of SPC to help control the Production Process.
2 QA Manager Upon receiving suggestion (or having own idea) for using SPC Suggestion; own ideas or research Review idea and consider how the Production Process can improve by using statistical analysis. Discuss with the process owners, QC Supervisors, Production Supervisors or Superintendent.  
3 QA Manager possibly with others Upon deciding to implement SPC on a process Prints, product dimensions and tolerances Develop and implement a data collection configuration into SPC Software Program, Infinity Proficient or equivalent. 
4 QA Manager After enough data has been gathered to generate analytical statistics Results of data collection Review the effectiveness of the new data collection configuration; determine if this configuration is collecting the information needed to analyze the process. 

If decide to discontinue, do so; if decide to continue system with modifications, go back to step 3; if decide to permanently continue system, go to step 5
5 QA Manager For forge and machine jobs requiring capability analysis or for internal capability analysis SPC Software Outputs Review the data collected utilizing SPC Software using capability charts, x-bar-r, historgrams, Pk, Cpk or other Software generated charts or reports to determine process stability.
6

QA Manager, Production Team Member  After reviewing SPC Software reports and charts Charts and reports from the SPC Software Program Analyze the trends and control during the production process.  Ask operators to note causes of out-of-control events.  See ISPEC-STATS for other trend and control events analysis tools. Discuss and Implement improvement opportunities.  Request a Corrective Action per TOP-CARRR as appropriate.
7

QA Manager As deemed appropriate Charts and reports from the SPC Software Program Review reports with customer if required.  Provide customer plan of action if warranted.

Revision history:

Release Date

Description of Change

Owner

Approver

12/06/2017

Updated to comply with revised Quality Manual and new TOPs format.

Tim Ellis

Todd Sheppard