Trinity Operating Procedures - TOPs
TOP-PSCHD: Shop Schedule
Rev: 2/22/2023
Scope: This procedure covers production and distribution of the manufacturing schedules..
Procedure:
STEP
WHO
WHEN
INFO
TO USE
WHAT
TO DO
1
Production Scheduler
Every workday; as needed
Job
Order release;
Synchronizer; Shop Schedules, BOMs and Routers
Release Job
Orders after
verifying material and die availability; schedule Job Orders that are
ready for production; execute and commit Synchronizer; update all
departments Shop Schedules; notify all Forging Superintendents/supervisors
that Shop Schedules
are ready; resolve scheduling problems to improve
delivery performance.
2 Department Managers/Supervisor Every workday Daily M2M Labor Input Reports;
Routers Review schedule and all open JO's for accuracy. 3 Department Managers/Supervisor Every workday Daily M2M Labor Input Reports;
Routers Based on schedule and production demands, ensure that each operation number reflects the equipment to be used. Update each Router in M2M as needed. 3A Department Managers/Supervisor Every workday Daily M2M Labor Input Reports;
Routers If router is a frozen process, contact Engineering or a QA Manager to validate that router update is allowed. 3B Engineering and/or QA Manager Receiving JO update request Update request; Process knowledge; Customer feedback Validate if JO request is allowed. Respond back with either approval to proceed or rejection including an explanation for why. 3C Department Managers/Supervisor Receiving Engineering/QA Manager Feedback Response from Engineering/QA Manager Update JO based on Engineering/QA Manager feedback.
If update is rejected, advise scheduler and await feedback on how to proceed. 4 Department Managers/Supervisor Change Required to in process JO Shop Schedules, BOMs and Routers Update JO as required. Reprint and replace current shop traveler with updated Traveler.
5
Any shop employee
If JO does not follow current process being performed
Job Traveler
Notify Manager/Supervisor immediately
of the discrepancy so a proper update can be made. Do not proceed until
updated JO Traveler is received.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
2/22/2023 |
Updated TOP's step 2-5 for JO update process. |
Dustin Jump |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|