TOP-MNTRM: Maintenance of Raw Material
Rev: 12/06/2017
Scope: This procedure is used when removing material from Steelyard inventory, for reasons other than cutting ticket procedures (tryouts, machine use, maintenance jobs, etc.)
Procedure:
NOTE:
The Materials Manager
needs to give approval to use any material in the
Steelyard. Due to the cost of material only the required amount for a
job may have been purchased.
STEP
WHO
WHEN
INFO TO USE
WHAT TO DO
1
Anyone needing steel for
special purpose
Before removing from Steelyard
Bundle
ID Tags; inventory info in M2M
After
bundle of material to be used is identified, contact Materials Manager
via email for approval to use; if approved to use get Inventory
Adjustment Ticket from Steelyard office and fill out
appropriate info;
if using full length of bar, place ticket in Steelyard office; if
returning cut length to inventory, return Inventory
Adjustment Ticket
to Steelyard office after bar is returned to correct Bundle ID. If not
approved to use, inquire when material needed will be available.
2
Materials
Manager
Email request for approval to
use specific material
Identification of material
requested
When receiving a request from
anyone requiring material for special purpose check inventory for
availability; give approval when there is sufficient quantity;
disapproval when there is not; advise when there will be material
available.
3
Steelyard
Supervisor
When Inventory
Adjustment Ticket is completed and placed in Steelyard office.
Inventory
Adjustment Ticket
Review Inventory
Adjustment Ticket; send to Materials
Manager.
4
Materials
Manager
Upon receiving Inventory
Adjustment Ticket
Inventory
Adjustment Ticket; inventory info in M2M
Make adjustments to inventory
to reflect status of material.
Revision history:
Release Date |
Description of Change |
Owner |
Approver |
12/06/2017 |
Updated to comply with revised Quality Manual and new TOPs format. |
Tim Ellis |
Todd Sheppard |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|